Line 26: | Line 26: | ||
===Cable routing plan for protoDUNE=== | ===Cable routing plan for protoDUNE=== | ||
− | [[File:cable_routing]] | + | [[File:cable_routing.png]] |
== Concerns and questions == | == Concerns and questions == |
Revision as of 15:34, 7 November 2016
Contents
Cable routing decision
Information on current status
APA Dimensions
APA opening dimensions (usable): 44mm x 63 mm (constrained by foot opening -> Can it be larger?)
Actual dimensions: 70mm x 95mm (see below for drawings)
Drawings:
Cable size
- PD cables: + PD head (xxmm x xxmm)
- Cold cables:
Cable routing plan for protoDUNE
Concerns and questions
- How difficult is it to bring the cables up in the APA frame? How long are the cables? What type of access we need to pass the cables through?
- Are there any mechanical difficulties to pass the cables up the APA frame? Weight? Space?
- Grounding and Shiedling: Can we bundle the cables together? Do we need mechanical/electrical separations in the APA frame?
- If we go along the cryostat wall, we need longer cables. What is the impact of longer cables on readout? Procurement?
- Is there anyway we can attached the cables on the cryostat wall? At the moment there is no mechanical
Group interface
- Inst.& Int.: Roxanne, Bill, Marvin
- APA: PSL (Lee and Dan) and Daresbury (Jo)
- PD: David, Leon and Gary
- CE: Matt
Potential testing sites
- Ash River (contact: Bill)
- Daresbury (contact: Jo)