Difference between revisions of "Installation and Integration/ActionItems/Cables"
Jump to navigation
Jump to search
Line 31: | Line 31: | ||
[[File:cable_routing.png]] | [[File:cable_routing.png]] | ||
− | [[File: | + | [[File:routing2.png|500px]][[File:routing1.png|500px]] |
== Concerns and questions == | == Concerns and questions == |
Revision as of 16:11, 7 November 2016
Contents
Cable routing decision
Information on current status
APA Dimensions
APA opening dimensions (usable): 44mm x 63 mm (constrained by foot opening -> Can it be larger?)
Actual dimensions: 70mm x 95mm (see below for drawings)
Drawings:
Cable size
- PD cables (Cat6): 9-10 mm diameter + PD head (18.5mm x 18.5mm). 5 cables per APA -> 10 cables in upper APA
- Cold cables: Max length = 25m (validated length for Gore), 20 CE cable pairs per APA (can they be split for each side of APA frame? -> 10 CE cable pairs per tube?)
-> CE cable pairs = data cables (26mm) + LV cables (xxmm)
Cable routing plan for protoDUNE
Concerns and questions
- How difficult is it to bring the cables up in the APA frame? How long are the cables? What type of access we need to pass the cables through?
- Are there any mechanical difficulties to pass the cables up the APA frame? Weight? Space?
- Grounding and Shiedling: Can we bundle the cables together? Do we need mechanical/electrical separations in the APA frame?
- If we go along the cryostat wall, we need longer cables. What is the impact of longer cables on readout? Procurement?
- Is there anyway we can attached the cables on the cryostat wall? At the moment there is no mechanical device on the inner cryostat membrane. The space between APA and membrane is ~15cm. Need to take the weight of the cables into account in this design solution.
Group interface
- Inst.& Int.: Roxanne, Bill, Marvin
- APA: PSL (Lee and Dan) and Daresbury (Jo)
- PD: David, Leon and Gary
- CE: Matt
Potential testing sites
- Ash River (contact: Bill)
- Daresbury (contact: Jo)