Action Items for the Installation and Integration group

1. Cryostat design

What is needed:


List of the components using the TCO

  • -> Who?

Roof penetration locations

  • Detector support structure interference
  • -> Jack

Cable routing to the feedthroughs

  • -> Who?


Floor loading

  • -> Who?

2. Underground space

Plan for the work flow

Ross Cage Design

Bill's proposal: [[1]]

Random information and questions

  • If we make the cage tall enough to fit the APA crate inside, the excavation equipment for CF may not fit inside because the cage reduces maximum width by ~4” (100 mm) as compared to a slung load
  • Making the cage taller also makes it heavier, reducing the weight capacity for both slung and cage loads
  • Can we do to the Yates shaft for some items? Boundary conditions.