Installation and Integration/ActionItems
Action Items for the Installation and Integration group
1. Cryostat design
TCO interface
- List of the components using the TCO
- -> Where is the info?
- -> Who?
- TCO dimensions
- Space inside needed to close the TCO
Roof penetration locations
- Detector support structure interference
- -> Jack
Cable routing to the feedthroughs
- -> Where is the info?
- -> Who?
Floor loading
The floor loading will probably be defined by the areal lift needed to reach the roof. A draft of the installation proceed needs revised and then the equipment at each step listed.
Main Steps are:
Installation of the detector support structure Installation of cryogenic piping, Detector installation.
I added info on the areal lift on the installation page.
- -> Where is the info?
- -> Who?
2. Underground space
Plan for the work flow
- -> Where is the info?
- -> Who?
Ross Cage Design
Bill's proposal: docdb entry
- -> Bill
Random information and questions
- If we make the cage tall enough to fit the APA crate inside, the excavation equipment for CF may not fit inside because the cage reduces maximum width by ~4” (100 mm) as compared to a slung load
- Making the cage taller also makes it heavier, reducing the weight capacity for both slung and cage loads
- Can we do to the Yates shaft for some items? Boundary conditions.