Difference between revisions of "Installation and Integration"
Jump to navigation
Jump to search
JimStewart (talk | contribs) |
JimStewart (talk | contribs) |
||
Line 4: | Line 4: | ||
The interface between the Conventional Facilities and the cryogenic/cryostat with the Far Detector are a major component of the integration group for DUNE. | The interface between the Conventional Facilities and the cryogenic/cryostat with the Far Detector are a major component of the integration group for DUNE. | ||
− | |||
===Key Documents=== | ===Key Documents=== | ||
Line 22: | Line 21: | ||
===Underground facilities=== | ===Underground facilities=== | ||
+ | |||
+ | ===Interface Management === | ||
+ | The interfaces between Conventional Facilities and the Far Detector are documented through a series of Interface Control Documents that are agreed upon by both LBNF and DUNE. The ICDs themselves generally only identify the interface and then refer to a separate key document to describe and define the interface. | ||
=Single-Phase Far Detector Installation= | =Single-Phase Far Detector Installation= |
Revision as of 16:19, 11 August 2016
Contents
Integration and Installation
Far Detector Integration
The interface between the Conventional Facilities and the cryogenic/cryostat with the Far Detector are a major component of the integration group for DUNE.
Key Documents
- LBNF BSI Pre-Excavation 60% Final Design Submission
- Comprehensive Logistics Plan
- LBNF EXC Pre-Excavation 60% Final Design Submission
Logistics
Surface Facilities
Ross Shaft
Underground facilities
Interface Management
The interfaces between Conventional Facilities and the Far Detector are documented through a series of Interface Control Documents that are agreed upon by both LBNF and DUNE. The ICDs themselves generally only identify the interface and then refer to a separate key document to describe and define the interface.