* CF Far Site Surface <--> Far Detector Design
+
* [http://docs.dunescience.org:8080/cgi-bin/ShowDocument?docid=196 CF Far Site Surface <--> Far Detector Design]
 
* CF Far Site Shafts and Drifts <--> Far Detector Design
 
* CF Far Site Shafts and Drifts <--> Far Detector Design
 
* CF Far Site Caverns <--> Far Detector Design
 
* CF Far Site Caverns <--> Far Detector Design

Revision as of 16:42, 11 August 2016

Integration and Installation

Far Detector Integration

The interface between the Conventional Facilities and the cryogenic/cryostat with the Far Detector are a major component of the integration group for DUNE.


Key Documents

Logistics

Surface Facilities

Ross Shaft

Underground facilities

Interface Management

The interfaces between Conventional Facilities and the Far Detector are documented through a series of Interface Control Documents that are agreed upon by both LBNF and DUNE. The ICDs themselves generally only identify the interface and then refer to a separate key document to describe and define the interface.

LBNF Systems Engineering webpage for interface management

Screen Shot Sys-Eng-web.png

Interface Control Documents

  • CF Far Site Surface <--> Far Detector Design
  • CF Far Site Shafts and Drifts <--> Far Detector Design
  • CF Far Site Caverns <--> Far Detector Design
  • CF Far Site Surface <--> Far Detector Construction
  • CF Far Site Shafts and Drifts <--> Far Detector Construction
  • CF Far Site Caverns <--> Far Detector Construction

Single-Phase Far Detector Installation

Dual-Phase Far Detector Installation

Miscellaneous

ENH1 Schedule